Each minute your team members are spent waiting on the elevator is wasted dollars spent.
We’ve developed a calculator so you can calculate how much money you could save each minute by reducing hoist delays. The outcome will help you determine the value of getting an additional elevator versus having your guys wait. Calculate costs savings.
Hoist Efficiency Calculator
Add your estimated costs below.
(up and down = 2 trips)
If multi shift, add in days
Average wait time in min | 10 | 9 | 8 | 7 | 6 | 5 | 4 | 3 |
Average tradesman cost with benefits per hour | [item-276_value] | [item-276_value] | [item-276_value] | [item-276_value] | [item-276_value] | [item-276_value] | [item-276_value] | [item-276_value] |
Average number of trips per man in a day (up and down=2) |
[item-315_value] | [item-315_value] | [item-315_value] | [item-315_value] | [item-315_value] | [item-315_value] | [item-315_value] | [item-315_value] |
Total unproductive min/day | 40 | 36 | 32 | 28 | 24 | 20 | 16 | 12 |
Wait time cost per man | 67 | 60 | 53 | 47 | 40 | 33 | 27 | 20 |
Duration of the project in weeks | [item-278_value] | [item-278_value] | [item-278_value] | [item-278_value] | [item-278_value] | [item-278_value] | [item-278_value] | [item-278_value] |
Working days per week | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] | [item-286_quantity] |
Total working days | 240 | 240 | 240 | 240 | 240 | 240 | 240 | 240 |
Number of tradesmen on a project | [item-287_value] | [item-287_value] | [item-287_value] | [item-287_value] | [item-287_value] | [item-287_value] | [item-287_value] | [item-287_value] |
Daily wait time cost | 6667 | 6000 | 5333 | 4667 | 4000 | 3333 | 2667 | 2000 |
Project wait time job cost | $1,600,000 | $1,440,000 | $1,280,000 | $1,120,000 | $960,000 | $800,000 | $640,000 | $480,000 |
You need to select an item to continue
Each minute saved in hoisting efficiencies:
The final estimated price is :
Average wait time in min | 10 | 9 | 8 | 7 | 6 | 5 | 4 | 3 |
Average tradesman cost with benefits per hour | [item-276_value] |
[item-276_value] |
[item-276_value] |
[item-276_value] |
[item-276_value] |
[item-276_value] |
[item-276_value] |
[item-276_value] |
Average number of trips per man in a day (up and down=2) |
||||||||
Total unproductive min/day | 40 | 36 | 32 | 28 | 24 | 20 | 16 | 12 |
wait time cost per man | ||||||||
Duration of the project in weeks | [item-278_value] |
[item-278_value] |
[item-278_value] |
[item-278_value] |
[item-278_value] |
[item-278_value] |
[item-278_value] |
[item-278_value] |
working days per week | [item-286_quantity] | [item-286_quantity] |
[item-286_quantity] |
[item-286_quantity] |
[item-286_quantity] |
[item-286_quantity] |
[item-286_quantity] |
|
total working days | ||||||||
number of tradesmen on a project | [item-287_value] |
[item-287_value] |
[item-287_value] |
[item-287_value] |
[item-287_value] |
[item-287_value] |
[item-287_value] |
[item-287_value] |
daily wait time cost | ||||||||
Project wait time job cost | 1,600,000 | 1,440,000 | 1,280,000 | 1,120,000 | 960,000 | 800,000 | 640,000 | 480,000 |
Enter your email.
Summary
Description | Information | Quantity | Price |
---|---|---|---|
Discount : | |||
Total : |